• This topic has 2 replies, 2 voices, and was last updated October 7, 2019 by IT O.

Shutdown of Recovery Data Centre

  • We have to shutdown our Recovery Data Centre, and I am wondering what the safe proceedure is for Source side.

    Should I simply pause all VPG’s and Zerto will automatically recover when the Hosts and storage are brought back online ?

    Thanks!

    Hello,

    This is Vladimir M with Zerto Support.

    Yes, you can pause the VPGs while the DR site is powered down. Please note that while the DR site is powered down, the VPGs will be in an error state until everything comes back online

    Thanks once again Vladimir – much appreciated. I shall proceed on this basis.