• This topic has 1 reply, 2 voices, and was last updated May 24, 2018 by Ryan S.

Failover test while delta synch in progress?

  • We just had a power failure in the primary site and all VPG’s are delta synching.  Is it OK to run a failover test on a VPG while the VPG is delta synching?

    Steve,

    You are not able to run a failover test on a VPG while that VPG is in the middle of a delta sync.

    The reason for this is because a delta sync is a complete resync of the replica disk so once that starts we can unmount that drive to spin up a test.

    I hope this helps to answer your question.

You must be logged in to create new topics. Click here to login