Journal retention after site disconnetion
You must be logged in to create new topics.
Click here to login
Assuming no LTR is in place, how long will journals be available on the DR site in the event of a disaster on the production site? Let’s say we have a planned outage to move equipment but we don’t want to initiate a failover. How long can that outage last and still be protected by Zerto?
Hi,
As far as i know the VPGs will go into error state but will still be recoverable until the journals are overwritten, and this will only occur when the sites can communicate
Regards
Chris